Client Information

St. Luke’s Hospital at The Village
Cliff Bottoms

Associate Vice President/Controller
20171 Chasewood Park Drive
Houston, Texas 77070
(832) 534-5909
cbottoms@sleh.com

Delivery Method
CM at Risk

Final Construction Cost
$160 Million

Building Size
227,000 sf

Accomplishments
Completed 8 months ahead of schedule and $5M under budget

Architect
Craig Holloway, Project Manager
Earl Swensson Associates
2100 West End Avenue
Vanderbilt Plaza, Suite 1200
Nashville, TN 37203
(615) 329-9445
craigh@esarch.com

Engineer
Aric Murray, VP – Chief Mechanical Engineer
Smith Seckman Reid, Inc.
3700 W. Sam Houston Pkwy. South, Suite 200
Houston, TX 77042
(713)784-8211
amurray@ssr-inc.com
St. Lukes Hospital at The Vintage
Greenfield Hospital – New Construction
Houston, Texas



St. Luke’s Hospital at The Vintage is a new 106-bed community hospital. The facility, which offers a full complement of medical and surgical services, is located on a 28-acre greenfield site in northwest Houston. A central goal of the project was to create an environment that promotes patient healing through the utilization of open spaces, natural light, noise reduction, and patient rooms that overlook large trees and water. The project construction was completed in approximately 15 months (8 months ahead of schedule). Additionally, 16 extra beds were added to the facility program and the final construction spend was $5 million less than the original budget.

Services Provided:

  • • Manage the Project Delivery Team Selection Process including the Construction Manager, Architect, Medical Equipment Planner, Telecommunications Planner, and Engineering Team
  • • Negotiate Construction Manager and Architect’s Fee and Contract terms and Conditions
  • • Master Budget and Schedule Development
  • • Management of Design Review and Value Enhancement Process
  • • Onsite Project Management Services